Decide What Counts as Better
Optional arithmetic and percentage refresher — return to this activity
A success criterion says what evidence would justify continuing. Set it before examining results to avoid moving the target until a preferred system wins. Quality, serious errors and effort can each matter; one attractive average need not override another gate.
Service desk trial: fictional workflow pack
All people, records and numbers in this pack are authored teaching examples. They are not records or performance claims about real organizations.
- F1 · Ten public practice requests, same task mix: the manual baseline used 80 minutes drafting, 20 reviewing and 20 repairing errors. Total hands-on work: 120 minutes. Nine final outputs were usable; no critical failures were recorded.
- F2 · Assisted draft workflow: 30 minutes drafting, normally 3 minutes review per request, 20 minutes repair and 30 minutes setup for this batch. Nine final outputs were usable; one unresolved disclosure of the wrong customer detail is a critical failure. All cases and outcomes are authored.
- F3 · Roles: intake clerk checks the request; assistant proposes a draft; reviewer compares it with permitted source records; service lead authorizes release. The reviewer can stop a draft; nothing here sends real messages.
- F4 · Exception trace: an action timed out. Receipt lookup for the same request ID shows “completed.” Repeating the action could create a duplicate. In a second trace the receipt cannot be found, so the outcome remains unknown.
- F5 · Trial gates agreed before comparison: at least 9 of 10 usable outputs, zero unresolved critical failures, and total batch work below 120 minutes. The ten exposed cases support development practice, not an untouched final evaluation.
- F6 · Count setup, review and repair for both methods. Hands-on minutes are not elapsed turnaround time. Waiting, service fees and broader operating costs are not measured by this small trial.
Check the whole batch and every gate
| Work | Manual | Assisted |
|---|---|---|
| Draft | 80 | 30 |
| Review | 20 | 10 × 3 = 30 |
| Repair | 20 | 20 |
| Setup | 0 | 30 |
| Total | 120 | 110 |
- Usable outputs: 9/10 → count gate passes.
- One unresolved critical failure → zero-failure gate fails.
- 110 minutes < 120 → effort gate passes.
The complete decision fails because all gates must pass. A 50-minute drafting reduction becomes only a 10-minute measured saving, and neither saving clears the critical failure.
Worked example
F5 requires at least 9 usable outputs, no unresolved critical failures and total work below 120 minutes for the same ten requests. F2 meets the usable-output count but has a critical failure, so saving time alone cannot justify rollout.
Use the supplied records to check facts and calculations. Your written reasoning is retained for your review, not automatically graded. The final project uses a different case and separate review criteria.